SWSG Logo



CWMBRAN STADIUM FIFA 2*


The project involved the construction of a new full size third Generation (3G) synthetic turf football pitch at Cwmbran Stadium. The synthetic surface has been built to replace the existing natural grass pitch and has been constructed to Fifa 2* certification. Works included top soil strip, geotextile membrane layers, drainage, sub-base stone & performance stone layers and carpet installation. All works were undertaken by South Wales Sports Grounds operatives.

Site Address: Cwmbran Stadium, Henllys Way, Cwmbran, NP44 3YS

Contact: Julia Goddard, Alliance Leisure - 07971 273150

Contract Value: Approx. £370,000
Construction Duration: 12 weeks
Completion Date: June 2015


“Alliance Leisure engaged the services of South Wales Sports Grounds to undertake the conversion of the grass pitch in the centre of the athletics stadium at Cwmbran to a 3G full sized pitch and futsal court.
SWSG were outstanding pre-contract, diligently working through the planning conditions and have been a pleasure to work with once the project commenced on site. Communication has been easy, the site is tidy and the work force knowledgeable. I would recommend SWSG as a reliable and good contractor to work with.” – Julia Goddard.